The year long evaluation of the Safety Modification to US 1 between SE 10th Street and George Bush Blvd is now complete.
The Executive Summary (300 kb pdf) comprises data collected in 2007 and 2009.
The US 1 Corridor Study (3 mb pdf) presentation provides detailed information on the US 1 Safety Modification test results.
FUNDING SOURCE
Construction costs for the permanent safety improvements are estimated to be approximately $11 million and the following funding has already been committed and/or requested:
$1,400,000 Federal Earmark with SAFETEA-LU Transportation Bill
$ 750,000 Federal Enhancement Grant
$2,000,000 State Funding for SE/NE 5th Ave RRR
$2,000,000 State Funding for SE/NE 6th Ave RRR
$ 350,000 Development Projects along both SE/NE 5th & 6th Ave
$4,500,000 Earmark Request from New Federal Transportation Bill
_________
$11,000,000 Total
Please note all design/engineering costs will be paid for by the Delray Beach Community Redevelopment Agency.
RRR = Resurfacing, restoration and rehabilitation